Tugu Barat Expansion

Medium Size Modular Gas Plant - Pertamina EP & PT. SDK

 

Data and Overview

Project Data

Utilize Flare's Gas with 38% CO2 content from Tugu Barat Complex Field to be process and produce LPG, Condesate & Lean Gas.

Project Location : Tugu Barat field - Indramayu, West Java
Term of Contract : Build, Operate and Transfer (BOT)
Contract Period : 10 years
Feed Gas Supply : 10 MMSCFD

Overview

PT. SDK operated Tugu Barat LPG Plant since 1995 for 10 years BOT contract. The first BOT contract was ended on December 31st, 2005. The expansion was based on the study made on the year 2003, and found that the gas resources in Tugu Barat area are still sufficient to feed the existing plant for the next 10 years and also having a potential to expand the capacity from current capacity of 6.5 MMSCFD to 10 MMSCFD. The new project construction was successfully been done without disturbing the current LPG plant operation, and start the commercial operation in July 2008.
 